This week’s updates from the Wisconsin Department of Transportation (WisDOT) on road construction projects for Barron, Burnett, Polk, Rusk, Sawyer, and Washburn counties.
Barron County
Highway: US 53 South
- Location: Bridges over US 8, 20th Street, Knapp Street, County I, Chetek River, County A, County AA and Carlson School Road between Cameron and New Auburn
- Schedule: May 5 to mid-November, 2025 construction; March 1 to late September, total project completion.
- Cost: $10.91 million
- Description of 2025 work: Replacing the decks on the bridges over County AA and County A; overlaying the decks with concrete on structures over Carlson School Road, Knapp Street and US 8; making miscellaneous repairs to bridges; completing prep work for 2026 construction on the bridges over the Chetek River, County I and 20th Street; and replacing guardrail at the structures.
- Traffic impacts: US 53 South remains open to traffic, but:
- Motorists will encounter lane closures and a reduced speed limit of 60 mph.
- In areas with lane closures, there is a maximum width of 15 ¼ feet on the open lane on the structure and 16 feet on the open lane of US 53.
- Motorists also will encounter intermittent daytime closures of the roads below the bridges during the work week.
Highway: US 63
- Location: Just west of WIS 48 West to Charrie Lane in Cumberland
- Schedule: April 28 to mid-September
- Cost: $3.68 million
- Description: Removing 3.25 inches of the existing pavement and placing 3.25 inches of new asphalt pavement; closing access to the roadway at various locations to improve safety; upgrading pedestrian curb ramps to current Americans With Disabilities Act standards; repairing or replacing curb, gutter and sidewalk; repairing sanitary sewer manholes and storm water inlets as needed; extending the two-way left-turn lane pavement markings between 3rd and 5th avenues; and replacing pavement markings and signage.
- Traffic impacts: US 63 remains open to traffic, but:
- North- and southbound traffic has 12-foot travel lanes through the entire project.
- The parking lane and shoulder are closed along the southbound lane.
Highway: US 53
- Location: 26th Avenue north of Rice Lake to Pine Grove Road south of Sarona
- Schedule: Sept. 5, 2023, to late May 2025
- Cost: $21.89 million
- Description of 2025 work: Tensioning cable barrier in the median between 26th and 27th avenues to reduce crossover crashes; placing a high-friction surface treatment on the pavement in the same area to reduce crossover and run-off-the-road crashes; removing and replacing a concrete joint, which will result in a several-day closure of a southbound US 53 lane; and placing final pavement markings.
- Traffic impacts: US 53 is open to traffic, but motorists will encounter lane closures in both directions through the weekend.
- Single-lane closures in both directions will continue the week of May 12 as crews apply a high-friction surface treatment on US 53; that work is expected to be completed sometime the week of May 19.
Burnett County
- No current projects
Polk County
Highway: County B
- Location: County Z to WIS 35/48 north of Luck
- Schedule: April 25 to late August
- Cost: $2.78 million
- Description: Pulverizing and relaying the existing pavement, paving the road with asphalt and completing shoulder work.
- Traffic impacts: County B remains open to traffic, but motorists might encounter lane closures controlled by flagging during work hours.
Highway: County F
- Location: View Lane east of Dresser to WIS 65 south of Balsam Lake
- Schedule: May 5 to June 17
- Cost: $1.14 million
- Description: Milling a portion of the existing pavement, placing new asphalt pavement, adding shoulder gravel and replacing pavement markings.
- Traffic impacts: County B remains open to traffic, but motorists will encounter lane closures controlled by flagging during work hours.
Highway: County W
- Location: McKenzie
- Schedule: April 25 to late August
- Cost: $2.78 million
- Description: Pulverizing and relaying the existing pavement, paving the road with asphalt and completing shoulder work.
- Traffic impacts: County B remains open to traffic, but motorists might encounter lane closures controlled by flagging during work hours.
Rusk County
- No current projects
Sawyer County
- No current projects
Washburn County
Highway: US 53
- Location: 26th Avenue north of Rice Lake to Pine Grove Road south of Sarona
- Schedule: Sept. 5, 2023, to late May 2025
- Cost: $21.89 million
- Description of 2025 work: Tensioning cable barrier in the median between 26th and 27th avenues to reduce crossover crashes; placing a high-friction surface treatment on the pavement in the same area to reduce crossover and run-off-the-road crashes; removing and replacing a concrete joint, which will result in a several-day closure of a southbound US 53 lane; and placing final pavement markings.
- Traffic impacts: US 53 is open to traffic, but motorists will encounter lane closures in both directions through the weekend.
- Single-lane closures in both directions will continue the week of May 12 as crews apply a high-friction surface treatment on US 53; that work is expected to be completed sometime the week of May 19.
Regionwide Pavement Marking Project
Highway: Various
- Location: Barron, Sawyer, Polk, and Washburn counties.
- Schedule: April 28 to mid-October
- Cost: $1.97 million
- Description: Replacing epoxy centerlines, edge lines and special markings.
- Traffic impacts: Motorists will encounter moving lane closures or traffic diversions where crews are working.
Last Update: May 10, 2025 12:18 pm CDT