Northwest WI Regional Construction Update - Nov. 17, 2023

Road construction project updates for Barron, Burnett, Polk, Rusk, Sawyer, and Washburn counties.

Northwest WI Regional Construction Update - Nov. 17, 2023

This week’s updates from the Wisconsin Department of Transportation (WisDOT) on road construction projects for Barron, Burnett, Polk, Rusk, Sawyer, and Washburn counties.

Note: With all projects seemingly completed, this will likely be our last Friday update for the year until construction projects begin again in the spring of 2024.


Barron County

  • No current projects

Burnett County

  • No current projects

Polk County

Highway: County K

  • Location: Branch Wapogasset Bridge west of Amery
  • Schedule: Sept. 12 to November
  • Cost: $595,977
  • Description: Replacing the bridge.
  • Traffic impacts: None; project complete.

Rusk County

  • No current projects

Sawyer County

  • No current projects

Washburn County

Highway: WIS 70

  • Location: Yellow River culvert east of the city of Spooner
  • Schedule: Aug. 7 to November (Updated)
  • Cost: $1.13 million
  • Description: Removing the existing culvert, constructing a bridge, replacing the pavement on both sides of the structure and placing new pavement markings and signage.
  • Traffic: None; project complete.

Last Update: Nov 17, 2023 8:42 am CST